Design and build contract to construct a high-end Logistic Hub with sustainability initiatives of LEED Certification located in Bandar Bukit Raja 2 Industrial Park, Klang. Our scope is as the main contractor which includes design and construct piling and substructure works, as well as superstructure and architectural, mechanical and electrical works for a two store ramp up warehouse with mezzanine level at each floor, a staff cafeteria facility, a show gallery, security warehouse, refuse chamber and electrical substation.
COMMENCEMENT DATE | CONTRACTUAL COMPLETION DATE | ACTUAL COMPLETION DATE | DAYS AHEAD OF SCHEDULE |
29 December 2022 | 28 September 2024 | 28 August 2024 | 31 Days |